Rural electrification of Ardfert, Co Kerry in 1949

Area: Ardfert
Started: August 1948
Finished: April 1949
Poles used: 1078
Line used (km): 82
Premises connected: 207

Ardfert-map-2-tralee

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

According to The REO News from December 1948 appliance sales were booming in The KingdomArdfert1-R.E.O.-December-1948-P

Ballyrobert farm Ardfert was featured in The REO News from April 1953Ardfert2-R.E.O.-April-1953-P

Leave a comment

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s