North Wall (1949-present)
This is an oil and gas station commissioned in 1949.
This is an active generating station.

River Liffey (1943-present)
Golden Falls, Poulaphuca and Leixlip are all hydro stations. They were commissioned in 1943, 1944 and 1949 respectively.
These three stations are still active.

Rural electrification of Kiltoom, Co Roscommon in 1949
Area: Kiltoom Started: July 1949 Finished: November 1949 Poles used: 269 Line used (km): 19 Premises connected: 233 The figures

Rural electrification of Moneenroe, Co Kilkenny in 1949
Area: Moneenroe Started: July 1949 Finished: December 1949 Poles used: 689 Line used (km): 58 Premises connected: 252 The figures

Rural electrification of Coole, Co Westmeath in 1949
Area: Coole Started: May 1949 Finished: September 1949 Poles used: 641 Line used (km): 57 Premises connected: 60 The figures

Rural electrification of Knock, Co Mayo in 1949
Area: Knock Started: April 1949 Finished: December 1949 Poles used: 464 Line used (km): 37 Premises connected: 154 The figures

Rural electrification of Moore, Co Roscommon in 1949
Area: Moore Started: April 1949 Finished: June 1949 Poles used: 387 Line used (km): 34 Premises connected: 138 The figures

Rural electrification of Shandon, Co Waterford in 1949
Area: Shandon Started: January 1949 Finished: December 1949 Poles used: 1213 Line used (km): 102 Premises connected: 347 The figures

Rural electrification of Ballitore, Co Kildare in 1949
Area: Ballitore Started: January 1949 Finished: July 1949 Poles used: 923 Line used (km): 51 Premises connected: 191 The figures

Rural electrification of Templecarrig , Co Wicklow in 1949
Area: Templecarrig Started: January 1949 Finished: November 1949 Poles used: 480 Line used (km): 37 Premises connected: 16 The figures

Rural electrification of Kilpeddar , Co Wicklow in 1949
Area: Kilpeddar Started: January 1949 Finished: August 1949 Poles used: 539 Line used (km): 43 Premises connected: 118 The figures

Rural electrification of Esker, Co Dublin in 1949
Area: Esker Started: January 1949 Finished: October 1949 Poles used: 310 Line used (km): 24 Premises connected: 1 The figures

Rural electrification of Jobstown, Co Dublin in 1949
Area: Jobstown Started: January 1949 Finished: July 1949 Poles used: 652 Line used (km): 53 Premises connected: 52 The figures

Rural electrification of Ardfert, Co Kerry in 1949
Area: Ardfert Started: August 1948 Finished: April 1949 Poles used: 1078 Line used (km): 82 Premises connected: 207 The figures