Rural electrification of Ballivor, Co Meath in 1954

Area: Ballivor
Started: December 1953
Finished: July 1954
Poles used: 938
Line used (km): 83
Premises connected: 140

Ballivor-Map-dundalk-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

The REO News from August 1954 reports that sale were negligible in BallivorBallivor-R.E.O

Leave a comment

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s