Rural electrification of Conna, Co Cork in 1953

Area: Conna
Started: January 1953
Finished: July 1953
Poles used: 755
Line used (km): 65
Premises connected: 116

Conna-Nap-cork

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

Sales in Conna were extremely satisfactory according to The REO News from September 1953Conna-R.E.O.-September-1953-P