Rural electrification of Meath Hill, Co Meath in 1956

Area: Meath Hill
Started: September 1955
Finished: March 1956
Poles used: 909
Line used (km): 78
Premises connected: 290

Meath-Hill-Map-dundalk-big

The figures above were sourced from our REO News magazine Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

There was some unexpected trouble in Meath Hill as reported in The REO News from September 1956Meath-Hill-REO-News-Sept-19560021