Rural electrification of Dromod, Co Leitrim in 1953

Area: Dromod
Started: June 1953
Finished: December 1953
Poles used: 989
Line used (km): 86
Premises connected: 5

Dromod-Map-sligo-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

Construction was difficult in Dromod according to The REO News from February 1954Dromod-R.E.O.February-1954-P