Rural electrification of Crossboyne, Co Mayo in 1951

Area: Crossboyne Started: June 1951 Finished: December 1951 Poles used: 384 Line used (km): 30 Premises connected: 66 The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme. Unfortunately no further information is… Continue Reading


Rural electrification of Clarecastle, Co Clare in 1951

Area: Clarecastle Started: December 1950 Finished: October 1951 Poles used: 620 Line used (km): 56 Premises connected: 87 The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme. Unfortunately no further information is available… Continue Reading


Rural electrification of Mahercloone, Co Monaghan in 1951

Area: Maheracloone Started: December 1950 Finished: October 1951 Poles used: 1044 Line used (km): 85 Premises connected: 248 The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme. Unfortunately no further information is available… Continue Reading


Rural electrification of Bodyke, Co Clare in 1951

Area: Bodyke Started: August 1950 Finished: April 1951 Poles used: 895 Line used (km): 77 Premises connected: 372 The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme. The REO News from April 1951… Continue Reading


Rural electrification of Belcarra, Co Mayo in 1951

Area: Belcarra Started: August 1950 Finished: April 1951 Poles used: 837 Line used (km): 63 Premises connected: 314 The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme. The REO News from May 1951… Continue Reading


Rural electrification of Ballybrittas, Co Laois in 1951

Area: Ballybrittas Started: August 1950 Finished: June 1951 Poles used: 1262 Line used (km): 103 Premises connected: 200 The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme. Unfortunately no further information is… Continue Reading


Rural electrification of Mulhuddart, Co Dublin in 1951

Area: Mullhuddart Started: June 1950 Finished: February 1951 Poles used: 510 Line used (km): 40 Premises connected: 250 The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme. The REO News from April 1951… Continue Reading