Area: Doobally
Started: October 1958
Finished: January 1959
Poles used: 399
Line used (km): 35
Premises connected: 105

Doobally-Map-sligo-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

Doobally was a tough nut to crack according to The REO News from May 1959Doobaly-REO-News-May-1959-P18