Connecting Roscommon to the national grid
Electricity in the county before ESB Roscommon had electricity before the establishment of ESB in 1927. ESB's annual reports record

Roscommon rural areas
Read more about the 38 rural areas connected under the Rural Electrification Scheme in Roscommon between 1948 and 1963.

Rural electrification of Kiltoom, Co Roscommon in 1949
Area: Kiltoom Started: July 1949 Finished: November 1949 Poles used: 269 Line used (km): 19 Premises connected: 233 The figures

Rural electrification of Moore, Co Roscommon in 1949
Area: Moore Started: April 1949 Finished: June 1949 Poles used: 387 Line used (km): 34 Premises connected: 138 The figures

Rural electrification of Cootehall, Co Roscommon in 1959
Area: Cootehall Started: January 1959 Finished: July 1959 Poles used: 1350 Line used (km): 118 Premises connected: 195 The figures

Rural electrification of Kilkeevin, Co Roscommon in 1963
Area: Kilkeevin Started: October 1962 Finished: February 1963 Poles used: 680 Line used (km): 62 Premises connected: 281 The figures

Rural electrification of Breedoge, Co Roscommon in 1963
Area: Breedoge Started: January 1963 Finished: September 1963 Poles used: 712 Line used (km): 67 Premises connected: 388 The figures

Rural electrification of Ballyfarnon, Co Roscommon in 1953
Area: Ballyfarnon Started: October 1952 Finished: August 1953 Poles used: 418 Line used (km): 34 Premises connected: 114 The figures

Rural electrification of Dangan, Co Roscommon in 1957
Area: Dangan Started: July 1956 Finished: August 1957 Poles used: 1901 Line used (km): 171 Premises connected: 454 The figures

Rural electrification of Tibohine, Co Roscommon in 1963
Area: Tibohine Started: August 1962 Finished: February 1963 Poles used: 1035 Line used (km): 93 Premises connected: 576 The figures

Rural electrification of Lisacul, Co Roscommon in 1962
Area: Lisacul Started: January 1962 Finished: August 1962 Poles used: 1112 Line used (km): 86 Premises connected: 443 The figures

Rural electrification of Edmondstown, Co Roscommon in 1961
Area: Edmondstown Started: February 1961 Finished: July 1961 Poles used: 803 Line used (km): 70 Premises connected: 253 The figures

Rural electrification of Carraghs, Co Roscommon in 1960
Area: Carraghs Started: April 1960 Finished: August 1960 Poles used: 888 Line used (km): 76 Premises connected: 32 The figures

Rural electrification of Tully, Co Roscommon in 1960
Area: Tully Started: October 1959 Finished: April 1960 Poles used: 1104 Line used (km): 95 Premises connected: 200 The figures

Rural electrification of Rathallen, Co Roscommon in 1956
Area: Rathallen Started: September 1955 Finished: June 1956 Poles used: 1287 Line used (km): 119 Premises connected: 72 The figures