Connecting Monaghan to the national grid
Electricity in the county before ESB Monaghan had electricity before the establishment of ESB in 1927. ESB's annual reports record

Monaghan rural areas
Read more about the 23 areas connected under the Rural Electrification Scheme in Monaghan between 1948 and 1961.

Rural electrification of Derrylea, Co Monaghan in 1961
Area: Derrylea Started: July 1961 Finished: October 1961 Poles used: 993 Line used (km): 89 Premises connected: 380 The figures above were sourced

Rural electrification of Stranoodan, Co Monaghan in 1961
Area: Stranoodan Started: April 1961 Finished: October 1961 Poles used: 1430 Line used (km): 125 Premises connected: 426 The figures above were sourced from our REO

Rural electrification of Drumcall, Co Monaghan in 1961
Area: Drumcall Started: August 1960 Finished: May 1961 Poles used: 1118 Line used (km): 98 Premises connected: 121 The figures above were sourced from our REO

Rural electrification of Newbliss, Co Monaghan in 1961
Area: Newbliss Started: April 1960 Finished: February 1961 Poles used: 1599 Line used (km): 138 Premises connected: 439 The figures above were sourced from our REO

Rural electrification of Smithboro, Co Monaghan in 1960
Area: Smithboro Started: November 1959 Finished: June 1960 Poles used: 1526 Line used (km): 135 Premises connected: 290 The figures above were sourced from our

Rural electrification of Rockcorry, Co Monaghan in 1958
Area: Rockcorry Started: May 1958 Finished: December 1958 Poles used: 1366 Line used (km): 120 Premises connected: 432 The figures above were sourced from our REO

Rural electrification of Broomfield, Co Monaghan in 1958
Area: Broomfield Started: October 1957 Finished: April 1958 Poles used: 1086 Line used (km): 95 Premises connected: 254 The figures above were sourced from our REO

Rural electrification of Oram, Co Monaghan in 1958
Area: Oram Started: October 1957 Finished: June 1958 Poles used: 1516 Line used (km): 138 Premises connected: 367 The figures above were sourced from our

Rural electrification of Annaroe, Co Monaghan in 1957
Area: Annaroe Started: March 1957 Finished: October 1957 Poles used: 1392 Line used (km): 120 Premises connected: 365 The figures above were sourced from our REO

Rural electrification of Killyneill, Co Monaghan in 1957
Area: Killyneill Started: June 1956 Finished: January 1957 Poles used: 934 Line used (km): 80 Premises connected: 197 The figures

Rural electrification of Latton, Co Monaghan in 1956
Area: Latton Started: September 1955 Finished: September 1956 Poles used: 1432 Line used (km): 122 Premises connected: 257 The figures above were sourced from our REO

Rural electrification of Lough Egish, Co Monaghan in 1956
Area: Lough Egish Started: September 1955 Finished: April 1956 Poles used: 895 Line used (km): 75 Premises connected: 85 The figures above were sourced from our

Rural electrification of Annayalla, Co Monaghan in 1953
Area: Annayalla Started: August 1952 Finished: September 1953 Poles used: 1204 Line used (km): 105 Premises connected: 337 The figures above were sourced from our REO