Connecting Cavan
Electricity in the county before ESB Cavan had electricity before the establishment of ESB in 1927. ESB's annual reports record

Cavan rural areas
Read more about the 33 areas connected under the Rural Electrification Scheme in Co Cavan between 1949 and 1962.

Rural electrification of Carrickeeshil, Co Cavan in 1962
Area: Carrickeeshil Started: August 1961 Finished: January 1962 Poles used: 1250 Line used (km): 99 Premises connected: 458 The figures

Rural electrification of Moyer, Co Cavan in 1961
Area: Moyer Started: March 1961 Finished: September 1961 Poles used: 1145 Line used (km): 102 Premises connected: 100 The figures

Rural electrification of Kilconny, Co Cavan in 1961
Area: Kilconny Started: February 1961 Finished: July 1961 Poles used: 925 Line used (km): 80 Premises connected: 30 The figures

Rural electrification of Butlersbridge, Co Cavan in 1961
Area: Butlersbridge Started: October 1960 Finished: February 1961 Poles used: 930 Line used (km): 78 Premises connected: 1 The figures

Rural electrification of Carrickgorman, Co Cavan in 1961
Area: Carrickgorman Started: November 1960 Finished: April 1961 Poles used: 1235 Line used (km): 110 Premises connected: 169 The figures

Rural electrification of Maghera, Co Cavan in 1960
Area: Maghera Started: April 1960 Finished: November 1960 Poles used: 1570 Line used (km): 150 Premises connected: 142 The figures

Rural electrification of Nolagh, Co Cavan in 1960
Area: Nolagh Started: November 1959 Finished: May 1960 Poles used: 1209 Line used (km): 107 Premises connected: 158 The figures

Rural electrification of Shercock, Co Cavan in 1959
Area: Shercock Started: June 1959 Finished: November 1959 Poles used: 1558 Line used (km): 140 Premises connected: 314 The figures

Rural electrification of Crosskeys, Co Cavan in 1959
Area: Crosskeys Started: December 1958 Finished: May 1959 Poles used: 940 Line used (km): 84 Premises connected: 230 The figures

Rural electrification of Tonyduff, Co Cavan in 1959
Area: Tonyduff Started: December 1958 Finished: July 1959 Poles used: 1375 Line used (km): 120 Premises connected: 323 The figures

Rural electrification of Ballyhaise, Co Cavan in 1958
Area: Ballyhaise Started: May 1958 Finished: November 1958 Poles used: 1200 Line used (km): 101 Premises connected: 98 The figures

Rural electrification of Rassan, Co Cavan in 1958
Area: Rassan Started: April 1958 Finished: August 1958 Poles used: 835 Line used (km): 75 Premises connected: 180 The figures

Rural electrification of Killygarry, Co Cavan in 1956
Area: Killygarry Started: June 1956 Finished: October 1956 Poles used: 1190 Line used (km): 92 Premises connected: 170 The figures