Shannonbridge (1964-2003)
This was a peat station commissioned in 1964.
This is a decommissioned station

1962 IRRS tour of Ardnacrusha
On Saturday 1 September 1962, the Irish Railway Record Society (IRRS) organised the first passenger train ever to operate to

Novum washing machine brochure 1964
View this 1964 booklet on Novum Washing Machines

July covers of ESB Journal
View a selection of July covers from our staff magazine ESB Journal 1959 to 1969

Fire Rescue Heroes 1964
Read the successful brave rescue by ESB workmen from our staff journal in August 1964

Rural electrification of Doonpeter, Co Cork in 1964
Area: Doonpeter Started: July 1963 Finished: April 1964 Poles used: 1106 Line used (km): 99 Premises connected: 286 The figures

Rural electrification of Caherdaniel, Co Kerry in 1964
Area: Caherdaniel Started: August 1962 Finished: June 1964 Poles used: 1211 Line used (km): 98 Premises connected: 370 The figures above

Rural electrification of Ballycroy, Co Mayo in 1964
Area: Ballycroy Started: January 1964 Finished: April 1964 Poles used: 265 Line used (km): 56 Premises connected: 182 The figures above were sourced from our REO

Rural electrification of Glenhest, Co Mayo in 1964
Area: Glenhest Started: July 1963 Finished: August 1964 Poles used: 761 Line used (km): 62 Premises connected: 164 The figures above were sourced from our REO

Rural electrification of Tuosist, Co Kerry in 1964
Area: Tuosist Started: July 1963 Finished: September 1964 Poles used: 1258 Line used (km): 101 Premises connected: 242 The figures above were

Rural electrification of Rossinver, Co Leitrim in 1964
Area: Rossinver Started: September 1963 Finished: May 1964 Poles used: 1071 Line used (km): 86 Premises connected: 261 The figures above

Rural electrification of Drumdoo, Co Leitrim in 1964
Area: Drumdoo Started: August 1963 Finished: July 1964 Poles used: 1555 Line used (km): 137 Premises connected: 430 The figures above

Rural electrification of Castlecuffe, Co Laois in 1964
Area: Castlecuffe Started: August 1962 Finished: April 1964 Poles used: 1134 Line used (km): 108 Premises connected: 303 The figures above were sourced from our REO

Rural electrification of Dunbeacon, Co Cork in 1964
Area: Dunbeacon Started: July 1963 Finished: January 1964 Poles used: not recorded Line used (km): 10 Premises connected: 46 The figures above were sourced