Rural electrification of Clashmore, Co Waterford in 1958

Area: Clashmore
Started: April 1958
Finished: October 1958
Poles used: 1003
Line used (km): 86
Premises connected: 184

Clashmore-Map-waterford

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.