Rural electrification of Killygarry, Co Cavan in 1956

Area: Killygarry
Started: June 1956
Finished: October 1956
Poles used: 1190
Line used (km): 92
Premises connected: 170

Killygarry-Map-dundalk-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

The REO News from November 1956 tells us of a challenge that was met and defeated in KillygarryKillygarry-REO-News-Nov-19560014