Rural electrification of Ballylongford, Co Kerry in 1955

Area: Ballylongford
Started: April 1955
Finished: October 1955
Poles used: 1332
Line used (km): 90
Premises connected: 36

Ballylongford-Map-tralee

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

Sales in Ballylongford were moderate according to The REO News from January 1956Ballylongford-REO-News-Jan-19560004