Rural electrification of Adamstown, Co Wexford in 1956

Area: Adamstown
Started: September 1955
Finished: February 1956
Poles used: 1415
Line used (km): 128
Premises connected: 242

Adamstown-Map-waterford

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

Prospects for additional sales looked good in Adamstown according to The REO News from May 1956Adamstown-REO-News-May-19560015