Rural electrification of Kilgarvan, Co Kerry in 1954

Area: Kilgarvan
Started: August 1953
Finished: June 1954
Poles used: 526
Line used (km): 42
Premises connected: 111

Kilgarvan-Map-tralee

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

The roads in Kilgarvan left a lot to be desired according to The REO News from August 1954Kilgarvan-R.E.O

Leave a comment

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s