Rural electrification of Oylegate, Co Wexford in 1953

Area: Oylegate
Started: August 1952
Finished: January 1953
Poles used: 753
Line used (km): 70
Premises connected: 154

Oylegate-Map-waterford

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.