Area: Kinnitty
Started: December 1954
Finished: July 1955
Poles used: 685
Line used (km): 62
Premises connected: 110

Kinnity-Map-athlone-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean.

The map above shows the area boundary and is from a digitised version of the original map used during the scheme. Unfortunately no further information is available for this area in the REO magazine.

As we work through the process of digitising our collections, if we find any other content for this area then we will publish it here.