Area: Killucan-Kinnegad
Started: September 1949
Finished: May 1950
Poles used: 1363
Line used (km): 118
Premises connected: 220

Killucan-map-athlone-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

A report on Killucan-Kinnegad made heartening reading according to The REO News from July 1950Killucan-KinnegadR.E.O.-July-1950-P

Bracklyn Farm Killucan was the featured farm in The REO News from June 1953Killucan-Kinnegad-R.E.O.-June-1953-PKillucan-Kinnegad-3-R.E.O.-June-1953-P

Leave a comment

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s