Rural electrification of Cross, Co Clare in 1955

Area: Cross
Started: June 1954
Finished: February 1955
Poles used: 672
Line used (km): 64
Premises connected: 154

Cross-Map-Limerick-(1)

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

The REO News from May 1955 reports that Cross was a windswept areaCross-R.E.O

Leave a comment

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s