Rural electrification of Ballintober, Co Mayo in 1954

Area: Ballintober
Started: August 1953
Finished: April 1954
Poles used: 1045
Line used (km): 93
Premises connected: 352

Ballintubber-Map-GALWAY-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

The REO News from June 1954 tells us that three types of holes were encountered in BallintoberBallintubber-R.E.O