Rural electrification of Ballinagh, Co Cavan in 1955

Area: Ballinagh
Started: August 1954
Finished: July 1955
Poles used: 1187
Line used (km): 105
Premises connected: 316

Ballinagh-MAP-dundalk-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

Ballinagh is rich in historical association according to The REO News from August 1953Ballinagh-R.E.O

Leave a comment

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s