Rural electrification of Cordal, Co Kerry in 1954

Area: Cordal
Started: June 1954
Finished: October 1954
Poles used: 1886
Line used (km): 157
Premises connected: 300

Cordal-Map-tralee

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

Backsliding was almost non existent in Cordal according to The REO News from November 1954Cordal-R.E.O

Leave a comment

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s