Area: Riverstown
Started: January 1949
Finished: January 1950
Poles used: 1023
Line used (km): 81
Premises connected: 290

Riverstown-map-sligo-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.