Rural electrification of Moore, Co Roscommon in 1949

Area: Moore
Started: April 1949
Finished: June 1949
Poles used: 387
Line used (km): 34
Premises connected: 138

Moore-map-athlone-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

The sales van was busy in Moore according to The REO News from August 1950 Moore-R.E.O.-August-1950-P