Rural electrification of Knockmore, Co Mayo in 1954

Area: Knockmore
Started: August 1953
Finished: April 1954
Poles used: 1557
Line used (km): 139
Premises connected: 566

Knockmore-Map-sligo-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

The REO News From May 1954 reports that Knockmore was not an easy areaKnockmore-R.E.O.-May-1954-P