Area: Jobstown
Started: January 1949
Finished: July 1949
Poles used: 652
Line used (km): 53
Premises connected: 52

Jobstown-map-dublin

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean.

The map above shows the area boundary and is from a digitised version of the original map used during the scheme. Unfortunately no further information is available for this area in the REO magazine.

As we work through the process of digitising our collections, if we find any other content for this area then we will publish it here.