Rural electrification of Farnaght, Co Leitrim in 1956

Area: Farnaght
Started: July 1956
Finished: October 1956
Poles used: 2028
Line used (km): 158
Premises connected: 83

Farnaght-Map-sligo-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

High hedges were an issue in Farnaght reports The REO News from February 1957Farnaght-REO-News-Feb-19570013