Rural electrification of Delvin, Co Westmeath in 1950

Area: Delvin
Started: May 1950
Finished: October 1950
Poles used: 972
Line used (km): 84
Premises connected: 104

Delvin-Map-athlone-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

The REO News from January 1951 reports that labour was scarce in DelvinDelvin-R.E.O.-January-1951-P