Rural electrification of Dangan, Co Roscommon in 1957

Area: Dangan
Started: July 1956
Finished: August 1957
Poles used: 1901
Line used (km): 171
Premises connected: 454

Dangan-Msligo-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

The REO News from September 1957 reports that rock was a problem in DanganDangan-REO-News-Sept-19570013