Rural electrification of Crossakiel, Co Meath in 1951

Area: Crossakiel
Started: August 1950
Finished: March 1951
Poles used: 895
Line used (km): 91
Premises connected: 97

Crossakiel-Map-dundalk-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

There were some adverse weather conditions in Crossakiel according to The REO News from April 1951Crossakiel-R.E.O.-April-1951-P

Leave a comment

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s