Rural electrification of Abbeydorney, Co Kerry in 1950

Area: Abbeydorney
Started: April 1950
Finished: December 1950
Poles used: 961
Line used (km): 88
Premises connected: 104

Abbeydorney-Map-tralee

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

Work in Abbeydorney was difficult due to the amount of water encountered as reported in The REO News from February 1951Abbeydorney-R.E.O.-February-1951-P

Leave a comment

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s