Started: April 1950
Finished: December 1950
Poles used: 961
Line used (km): 88
Premises connected: 104

Abbeydorney-Map-tralee

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

Work in Abbeydorney was difficult due to the amount of water encountered as reported in The REO News from February 1951Abbeydorney-R.E.O.-February-1951-P