Rural electrification of Muff, Co Donegal in 1956

Area: Muff
Started: September 1955
Finished: January 1956
Poles used: 607
Line used (km): 50
Premises connected: 160

Muff-Map-sligo-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

Water pumps were a good seller in Muff according to The REO News from April 1956Muff-REO-News--Apr-19560005