Rural electrification of Emly, Co Tipperary in 1949

Area: Emly
Started: August 1948
Finished: March 1949
Poles used: 1641
Line used (km): 140
Premises connected: 560

Emly-map-limerick

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

The REO News reports on a hurling match in Emly from the May 1949 issueEmly1-R.E.O.-May-1949-P
_Emly2-R.E.O.-May-1949-P