Rural electrification of Culdaff, Co Donegal in 1958

Area: Culdaff
Started: October 1957
Finished: April 1958
Poles used: 1222
Line used (km): 105
Premises connected: 313

Culdaff-Map-ESB-MAP-SLIGO-XLARGE

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

Culdaff was mentioned briefly in The REO News from October 1958Culdaff-REO-News-Oct-19580009