Rural electrification of Aglish, Co Tipperary in 1951

Area: Aglish
Started: June 1951
Finished: December 1951
Poles used: 575
Line used (km): 49
Premises connected: 42

Aglish-Map-athlone-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

The REO News from November 1951 reports on the benefits of storage heating in Aglish Aglish-R.E.O.-November-1951-P