Rural electrification of Rathkenny, Co Meath in 1953

Area: Rathkenny
Started: January 1953
Finished: October 1953
Poles used: 965
Line used (km): 88
Premises connected: 242

Rathkenny-Map-dundalk-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

The REO News from November 1953 reports that there were two major difficulties in RathkennyRathkenny-R.E.O