Rural electrification of Manor, Co Donegal in 1952

Area: Manor
Started: June 1951
Finished: August 1952
Poles used: 1130
Line used (km): 91
Premises connected: 37

Manor-Map-sligo-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.