Rural electrification of Glinsk, Co Roscommon in 1954

Area: Glinsk
Started: May 1953
Finished: February 1954
Poles used: 1055
Line used (km): 101
Premises connected: 336

Glinsk-Map-athlone-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

There were bargains to be had in Glinsk according to The REO News from April 1954Glinsk-R.E.O.-April-1954-P