Rural electrification of Kilcurry, Co Louth in 1950

Area: Kilcurry
Started: December 1949
Finished: September 1950
Poles used: 998
Line used (km): 99
Premises connected: 266

Kilcurry-Map-dundalk-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

According to The REO News From October 1950 a report from Kilcurry makes interesting readingKilcurry-R.E.O.-October-1950-P

Leave a comment

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s