Rural electrification of Kilcar, Co Donegal in 1952

Area: Kilcar
Started: December 1950
Finished: March 1952
Poles used: 822
Line used (km): 71
Premises connected: 248

Kilcar-Map-sligo-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

There was only one backslider in Kilcar according to The REO News from November 1952Kilcar-1-R.E.O.-November-1952-P Kilcar-2-R.E.O.-November-1952-P Kilcar-3-R.E.O.-November-1952-P