Rural electrification of Barnaderg, Co Galway in 1955

Area: Barnaderg
Started: September 1955
Finished: December 1955
Poles used: 442
Line used (km): 42
Premises connected: 150

Bernaderg-Map-GALWAY-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

The REO News from March 1956 notes that Barnaberg was a small areaBernaderg-REO-News--Mar-19560006