Area: Boston
Started: June 1956
Finished: October 1956
Poles used: 631
Line used (km): 60
Premises connected: 90
The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.
The REO News from January 1957 informs us that sales were reasonable in Boston