Rural electrification of Pollroan, Co Kilkenny in 1948

Area: Pollroan
Started: December 1947
Finished: April 1948
Poles used: 1145
Line used (km): 91
Premises connected: 72

Pollroan-map-waterford

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

Pollroan was slow to embrace the scheme but eventually warmed to it as reported in the October 1949 issue of the REO NewsPollroan1-R.E.O.-October-P

Leave a comment

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s