Rural electrification of Julianstown, Co Meath in 1948

Area: Julianstown
Started: December 1947
Finished: September 1948
Poles used: 1458
Line used (km): 119
Premises connected: 327

Julianstown-map-2-dundalk-big

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

The resourcefulness of the rural staff knew no bounds as this example from The REO News of June 1948 showsJulianstown-R.E.O.-June-1948-P

Leave a comment

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s