Rural electrification of Knocknagree, Co Cork in 1949

Area: Knocknagree
Started: January 1949
Finished: December 1949
Poles used: 1182
Line used (km): 98
Premises connected: 263

Knocknagree-map-tralee

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

The REO News from December 1954 reports on an encounter with the poet Ned Buckley of KnocknagreeKnocknagree-2-R.E.O

Knocknagree-3-R.E.O

Leave a comment

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s