Area: Freemount
Started: December 1954
Finished: November 1955
Poles used: 1500
Line used (km): 143
Premises connected: 271
The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.
There was a satisfactory report from Freemount according to The REO News from February 1956