Rural electrification of Carrignavar, Co Cork in 1953

Area: Carrignavar
Started: March 1952
Finished: March 1953
Poles used: 857
Line used (km): 83
Premises connected: 153

Carrignavar-Map-cork

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

There was a high level of sales in Carrignavar according to The REO News from May 1953Carrignavar-R.E.O.-May-1953-P