Rural electrification of Ballyhay, Co Cork in 1954

Area: Ballyhay
Started: June 1954
Finished: December 1954
Poles used: 1400
Line used (km): 126
Premises connected: 370

Ballyhay-Map-limerick

The figures above were sourced from our REO News magazine. Click here to find out more on what the figures mean. The map above shows the area boundary and is from a digitised version of the original map used during the scheme.

The REO News from March 1955 had a very satisfactory report from BallyhayBallyhay-R.E.O